FEBRUARY 2022

Construction of Bridge Reaches Final Stages

Suite and common area finishing is well underway, working toward July occupancy.

How is construction progressing?

The first few months of 2022 have brought construction of the Bridge into the final stages, working toward turnover and occupancy in July of 2022.  The elevators are installed, and the person/material hoist has been removed from the exterior of the building.  The exterior cladding is currently being installed and is expected to be complete in spring.

Suite and common area finishes are ongoing with drywall, taping, and sanding complete in all suites, and other finishes follow close behind.  Commissioning of various mechanical and electrical systems is underway and will be ongoing up until completion.

What are the working hours?

A typical workday during this phase will be from 7 AM to 5:30 PM, though some days could extend to 8:00 PM.

Is there going to be a lot of noise and dust?

Exterior works will be limited to cladding and roofing which will have minimal noise impact. Noise will be limited to daytime activities going forward.

Who is the contact person for questions or concerns about construction at The Bridge?

We understand that the construction process can feel disruptive for people living nearby the site.  Anyone with questions or concerns about how work is progressing at The Bridge is encouraged to reach out to Mike Bakgaard ITC Site Superintendent via email at mbakgaard@itc-group.com or Ron Jordan, ITC Senior Project Manager via email at RJordan@itc-group.com.