MAY 2023

Spring Brings Construction Progress at Hive

The mild spring weather is helping the construction team keep up a brisk pace.

How is construction progressing?

What a great spring! Concrete is progressing well and should see some big movement upward in the next two months and up to Level 6 by the end of July.

 

What are the working hours?

A typical workday remains from 7AM to 5:30PM, though some days work could extend to 8:00PM or later depending on how the concrete pour days play out.

 

Is there going to be a lot of noise and dust?

As with any construction project, there will be some loud banging and some noise associated with our equipment and the delivery and pouring of concrete and other heavy materials.  On windy days, our Construction Manager will try to modify work whenever possible to minimize blowing dust but now that we are out of the ground, dust will be reduced.

 

Who is the contact person for questions or concerns about construction at Hive?

We understand that the construction process can feel disruptive for people living nearby the site.  Anyone with questions or concerns about how work is progressing at Bridge is encouraged to reach out to us by filling out an online form at jemm.ca/the-hive-in-sunnyside.